Rural Electrification Phase II
Project Summary
(i) increased efficiency of energy supply by EdL and consumption by customers; and (ii) substantial adoption of renewable energy in Government’s rural electrification program. GHG emissions reductions are expected from increased energy efficiency as increased hydropower exports to and reduced electricity import from Thailand reduce thermal power production in Thailand; and from renewable energy development to avoid diesel-based electricity generation for rural electrification.
Project Details
| GEF Project ID | 4152 |
| Project Type | Full-size Project |
| Status | Completed |
| Country | Lao PDR |
| Region | |
| Focal Areas | |
| Funding Source | GEF Trust Fund |
| Implementing Agencies | The World Bank |
| Executing Agencies | Electricité du Laos and Ministry of Energy and Mining |
| GEF Period: | GEF - 4 |
| Approval Fiscal Year: | 2010 |
Project Documents
Financials
| Project Preparation Grant Amount | 0 USD |
| GEF Project Grant | 1,818,000 USD |
| Co-financing Total | 8,630,000 USD |
| GEF Agency Fees | 181,800 USD |
| Total Cost | 10,448,000.00 USD |
Project Timeline
Received by GEF
26 Oct 2009
Concept Approved
31 Mar 2010
Project Approved for Implementation
24 Jan 2011
Project closed
07 Dec 2015