Sustainable Development of Comoros Islands by Promoting the Geothermal Energy Resources
Project Summary
To promote geothermal energy resource development in the country for base-load electricity generation.
Project Details
| GEF Project ID | 9040 |
| Project Type | Full-size Project |
| Status | Project Approved |
| Country | Comoros |
| Region | |
| Focal Areas | |
| Funding Source | GEF Trust Fund |
| Implementing Agencies | United Nations Development Programme |
| Executing Agencies | UNDP – National Implementation Modality |
| GEF Period: | GEF - 6 |
| Approval Fiscal Year: | 2016 |
Financials
| Project Preparation Grant Amount | 140,000 USD |
| GEF Project Grant | 5,905,662 USD |
| Co-financing Total | 48,360,000 USD |
| GEF Agency Fees | 561,038 USD |
| Total Cost | 54,405,662.00 USD |
Project Timeline
Received by GEF
27 Feb 2015
Preparation Grant Approved
04 May 2016
Concept Approved
01 Jun 2016
Project Approved for Implementation
28 Jan 2018
Project closed