Enhancing Conjunctive Management of Surface and Groundwater Resources in Selected Transboundary Aquifers: Case Study for Selected Shared Groundwater Bodies in the Nile Basin
Project Summary
To strengthen knowledgebase, capacity and cross-border institutional mechanisms for sustainable use and management of selected transboundary aquifers in the Nile Equatorial Lakes and Eastern Nile sub-basins.The transboundary aquifers that will be covered by the study and beneficiary countries sharing these aquifers are given in section describing the ‘alternative’. Final selection of the aquifers will be made during the PPG phase of the project.
Project Details
| GEF Project ID | 9912 |
| Project Type | Full-size Project |
| Status | Project Approved |
| Country | Regional |
| Region | |
| Focal Areas | |
| Funding Source | GEF Trust Fund |
| Implementing Agencies | United Nations Development Programme |
| Executing Agencies | Nile Basin Initiative (NBI) |
| GEF Period: | GEF - 6 |
| Approval Fiscal Year: | 2018 |
Project Documents
- FSP CEO endorsement document
- Review Sheet (PDF)
- GEFSEC Review
- 5783_GEF6 CEO ER NBI 29May2019 final
- STAP Review (PDF)
- PIF Document for WPI
- PIMS 5783_NBI ProDoc sub 25Oct2019
- PIMS 5783 UNDP Response Matrix 25Oct2019
- PIMS 5783_NBI ProDoc 12 09 2019 final
- PIMS 5783 GEFSec Review sheet - response sheet - 12 09 2019
- 5783_NBI ProDoc Final NBI 229May2019 final
- 5783_NBI ProDoc 11 07 2019 final upd by NBI to address GEFSec comments
- 5783_GEF6 CEO Endorsement NBI 11 07 2019 final upd by NBI to address GEF Sec comments
- 5783_GEF Core Indicators_UNDP_s Offline -NBI_11 07 2019 rev
- 5783_Annex I - Capacity Assessment
- 5783_GEF Core Indicators_UNDP_s Offline -NBI_11 07 2019
- 5783_GEF 7 Taxonomy_NBI
- 5783_GEF Core Indicators_UNDP_s Offline -NBI
- 5783_Annex E - Stakeholders engagement plan 10 07 2019
- 5783_Annex F - Gender Analysis and Action plan annex 10 07 2019
- 5783_Annex F - Gender Analysis and Action plan annex
- 5783_Annex G - Risk_Log
- 5783_Annex H - Co-financing letters_29052019
- 5783 GEFSec Review sheet - response sheet - 11 07 2019 final
- 5783_Annex B
- 5783_Annex D
- 5783_Annex E - Stakeholders engagement plan
Financials
| Project Preparation Grant Amount | 150,000 USD |
| GEF Project Grant | 5,329,452 USD |
| Co-financing Total | 25,850,000 USD |
| GEF Agency Fees | 506,298 USD |
| Total Cost | 31,329,452.00 USD |
Project Timeline
Received by GEF
05 Sep 2017
Preparation Grant Approved
30 Oct 2017
Concept Approved
01 Nov 2017
Project Approved for Implementation
07 Nov 2019
Project closed